In this chapter, we’ll explore a project planning tool called the program evaluation and review technique, otherwise known as PERT. The PERT technique uses charts to sequence different activities. Similar to the critical path method, it shows tasks, durations, and dependencies. These activities are time scaled to indicate approximately how long each activity lasts. The PERT chart and CPM both follow the same steps, and use network diagrams to plan and schedule individual activities necessary for a project. Even though they’re both useful in determining the earliest and latest start and finish times for each activity, there are a few differences between the two. The CPM chart is more deterministic. It presents estimates of activity duration that are based on historical data or information. Whereas the PERT chart is more probabilistic. It uses estimates based on uncertainty. Therefore, it typically uses ranges to represent the probability that an activity will fall into that range. On a PERT chart, each activity node provides information on the duration of that activity. In this example, the number on the left side of the top row is the earliest point at which the activity could start. The middle number is the duration, expressed in days, hours, minutes, or seconds. Or really, whatever’s relevant to your project. And the right-hand side indicates the earliest point in which the activity could finish. Additional information is included in the bottom row of the activity node. So in this example, the number on the bottom row on the left side is the latest start point. The number in the middle is any available slack time for that activity. And finally, the number on the bottom row on the right side is the latest possible finish point. The activity nodes are then joined together by arrows. And these arrows indicate any dependencies between these specific activities. When developing the PERT chart, a key aspect of it are the time estimates.
The team would develop this information to establish duration values. Typically, PERT charts are used on projects that are non-recurring or non-frequent. So you may not have sufficient historical data to determine exact values. Therefore, the PERT chart uses probabilistic estimates. You’re trying to find the probability that the duration will fall within a specific range. PERT charts use three point estimates. The first is the pessimistic time. Which is the maximum possible time that would be required to accomplish the task, assuming that everything goes wrong. The most probable time is the best estimate of time required to accomplish a task, assuming that everything proceeds as you would expect it to. And the optimistic time is the minimum time that would be required to accomplish a task, assuming that everything goes better than you would normally expect it to. Finally, there’s a fourth time, which is the expected time. This is the best estimate of the time that will be required to accomplish a task. And accounts for things not always going as expected, but realizing that some things could go a little better. The expected duration in a PERT chart is calculated by adding the optimistic duration estimate and the most likely duration. The value of M is then multiplied by 4, because these are 4 times more likely to happen than the others. The pessimistic duration estimate is then added to this value. And then the result is divided by 6 to get the weighted average of the time estimates. Now, let’s explore how you would calculate the expected duration to complete the design phase of a project. If there are no delays, the project will take no more than 6 weeks. However, based on past projects, the most probable estimate is 10 weeks. So you multiply that by 4. Then considering all the things that could go really wrong, you determine the pessimistic estimate to be 18 weeks. The top line formula gives you a value of 64 weeks. In order to get the weighted average, you then divide that amount by a value of 6. So the estimated duration of the project is 10.67 weeks.